Kleenheat
SRG Global
Kleenheat LPG Post Boost — Train 1 SMP
Contract 367043 · Kleenheat Production Facility, Kwinana · Structural, Mechanical & Piping
Baseline: Schedule & Resource Plan Rev E (27 Aug 2026)
SOW PD-2074-1100-0-SOW-0007 Rev 0.0.0
Mobilisation
31 Aug 2026
M1
Shutdown Window
16–22 Nov 2026
M6 · fixed · 7 days
Mechanical Completion
18 Dec 2026
M8
Overall Progress
Status
Pre-mobilisation
as-at 28 Aug 2026
Shutdown Window — Gating Constraints 16–22 Nov 2026 · 7 days · fixed

The window does not move. Four WesCEF attendances gate work inside it and none carries a committed response time; the plant is live from 22 November, so everything from 23 Nov to 18 Dec is live-plant work adjacent to LPG.

Isolation
Physical isolation proof before every cut — per boundary or per break, and duration, still TBA. The single most important number outstanding: per-break proof turns the 16–17 Nov demolition (738 h across both shifts) into a queue. Proposed answer date 26 Sep.
10.5 h
Radiography runs into shift handovers, 05:30–07:00 and the night equivalent. Effective tool time inside the exclusion zone drops from 12 h to about 10.5 h against durations built on 12 h. Exclusion radius not yet advised.
31 / 46
Tie-ins in the window — 15 cut-and-weld, 15 flanged, 1 screwed, of 46 active. Resourced at 4 teams/shift × 4 days × 2 shifts = 32 team-shifts against 31 in-window tie-ins.
44 heads
Peak manning Thu 19 – Sun 22 Nov (41 on Mon 16 Nov), across two 12 h shifts with 13 h supervision. Pre-shutdown peak 18; post-shutdown 21 on 14–15 Dec.

Also inside the window: line-break witness and end-to-end verification before any unbolting (SIMOPs), scaffold acceptance sign-off from Kleenheat including after in-window alteration, all plant and equipment off the job front each shift (VN-003, ~170 h effect on task 3.5 alone, ~10 %), and no welding habitat — so no pre-shutdown welding in the operating process area.

Milestone Register 0 items
ID Activity Date Week Notes
Weather Record & Lifting Outlook Kleenheat Production Facility, Kwinana · recorded actuals + 7-day outlook
Tile stateWind — 10-min mean, boom tipAction
Green < 7 m/s · < 25 km/h · < 13 kt Normal lifting
Amber 7–9 m/s · 25–33 km/h · 14–18 kt No new lifts started. Land what's in the air. No large sail-area, blind, or tandem lifts. Supervisor decision recorded.
Red > 9 m/s · > 33 km/h · > 18 kt Lifting stopped. Load landed and secured.
Chart max Per crane load chart, typically 9.8–11.1 m/s Never exceeded regardless of the above.

These are SRG control values, not a client limit. Nothing in the SOW, the permit-to-work system or the contract states a numeric wind limit; the table above is SRG's own trigger set and sits under the crane's load chart (AS 2550.1), which governs absolutely and falls sharply with sail area — the EC-12.01 skid (14,650 kg operating) is a large-area lift and will sit well below the generic chart figure. Each lift's stop-work number is the one written in its approved lift plan, submitted to the WesCEF Authorised Person before lifting.

A green tile is not clearance to lift. The tiles band a 10 m forecast against a table written for the boom tip. Wind rises with height, so the boom tip generally reads higher than what is drawn here. Gust is shown but never sets the band — the control quantity is the 10-minute mean. The trigger is the anemometer at the boom head on the day, not this page.

Legend
Done
Active (in progress)
On Track (not started)
At Risk
Delayed
Planned
Milestone (baseline)
Forecast PC (progress-based)
Bar fill = % complete
Today
Overrun (green = planned · yellow = +1 day · red = over target)
Activity WBS Status
Contract & Scope Basis
  • Contract 367043, executed as a deed 26 Aug 2026 · PO 61247912 Rev 0 · lump sum, 8 payment milestones
  • Scope of Work PD-2074-1100-0-SOW-0007 Rev 0.0.0, released 14 Jun 2026 (Schedule 1)
  • Pricing datum IFC Document Register Rev D, 11 Aug 2026 — later changes are variations
  • IFC documentation prevails over tender documentation (Contract Schedule 1)
  • Engineering by Worley, job no. 411012-01310 · client Wesfarmers LPG Pty Ltd (WesCEF / Kleenheat)
  • Baseline: Schedule and Resource Plan Rev E, 27 Aug 2026 (amended 28 Aug, task 1.4)
  • Site hours 10,616 over 85 working days · 1,011 head-days (Rev E)
  • Calendar: Sundays non-working outside the outage · King's Birthday Mon 28 Sep
Open Items not yet fact — do not report as progress
  • One agreed Date for Completion, and written confirmation the eight PO Deliver By dates are payment milestones, not eight LD triggers
  • Isolation proof basis — per boundary or per break, and duration. Gates the Level 5
  • RT exclusion radius — open with Enermech
  • Free-issue pipe support delivery date — Pipe Support Register still issued HOLD
  • Balance-of-material route — 79 m supply gap
  • Nine TQs requested 12 Aug, acknowledged 13 Aug, not provided
  • Site plan and facilities (SOW §1.6) — needed for gate, muster and laydown pins
  • Recipient nominated for cl. 13.4 and cl. 30.1 notices
  • Insurance certificates expired — Workers' Comp PE1000442GWC lapsed 30 Jun 2026; cl. 11.8 makes insurance compliance a condition of site access
  • Six-week fabrication clock from the complete free-issue set: 25 Sep + 6 wks = 6 Nov, against M4 on 30 Oct and M5 on 2 Nov
  • Three competing hold-point schemes (baseline H1/H3/H4/H5 vs ITP register H1–H16 vs WesCEF template) — reconcile before a hold-point count is shown
  • Weld Register shop/field split columns are blank — the denominator for weld progress does not yet exist
Interfaces who to go to, for what
NameOrgRoleGo to them for
Simon MooreWesCEFProject EngineerTQs, drawings, day-to-day direction, free issue
Rob MastagliaWesCEFConstruction APWork pack counter-signature, lift plan approval, scaffold acceptance
Rob SullivanWesCEFQualityITP approval, workshop interface, surveillance, SharePoint
Anthony SmithWesCEFSafety AdvisorJSAs, SMS §17.2, AP delegate training, engineered scaffold, dropped objects
Damian (surname TBC)WesCEFLiftingLift plans, "over live" ruling
Darryl (surname TBC)WesCEFScheduling / stagingSite plan, laydown, permits, insulation access, P6, SIMOPs
Suganthi SolaiyanWesCEFContract & commercialDate for Completion, milestones, payment
Chris CassonEnermechSite lead, NDTNDT request forms, RT windows, exclusion zone
GFSSubcontractorWorkshop NDT & hydro
Shield IndustrialSubcontractorInsulation prefabrication
GCS WASubcontractorCraneage
BE SurveysSubcontractorSurveyTP-12 survey (H1)

Enermech is contractual with WesCEF and operationally directed by SRG — added scope must carry added NDT authorisation automatically, and NDT reports plus NATA calibration certificates must still flow to SRG for the MDR.